Calendar and Milestones

Product Availability

CBAS-R will be ready for limited distribution on a pilot basis by fall 2007. The product will be distributed on a less limited basis in the fall of 2008. Districts, schools and agencies should contact Dr. Christ tchrist@umn.edu with questions.

Dissemination of Findings

Reports will be published online as the project progress through the fall of 2008. The content of some reports and other relevant findings will be prepared and submitted of publication through 2010.

Management: Time of Activities and Anticipated Outcomes

Timeline.

This project will be completed over a period of 24 months. In the first three months, activities will accomplish the Start-up Objectives: establish CBAS webpage, recruitment, human subjects, administrative procedures for the grant, and purchase necessary equipment for start-up. In the first eight months of the project (1/06 – 8/06), activities will accomplish. Objective 1: Develop the supporting materials to define the targets of measurement, a priori skills hierarchy, and construct items that will comprise the CBAS for early reading development. In the next 10 months of the project (8/06 – 6/07), activities will accomplish. Objective 2: Develop the supporting materials for the Computer Adaptive Test (CAT) component of the CBAS. In the final six months of the project (6/07 – 12/07), activities will accomplish. Objective 3: Develop supporting materials for the Adaptive Self Referenced Test (ASRT) component of the CBAS. Throughout the course of project, the CBAS technology will develop in stages to meet the final objective. Sequential development of CBAS technology will achieve the successive components that comprise objective 4. Objective 4: CBAS with CAT and ASRT components with utility for screening, leveling, skill analysis, progress monitoring, evaluating responsiveness to intervention, and examining developmental trends in reading. This is the primary objective defining the final CBAS product.

Milestones.

The project will be completed in 24 months. Milestones are identified that correspond with one start-up Objective along with Objectives 1 through 4. Progress will be systematically reviewed and evaluated by the both the Project Director and Advisory Board for the purpose of input, process, and outcome evaluations (see [d2.ii] Management: Continuous Feedback and Program Evaluation). Successful start-up will be established when the project accomplishes

Summary of Timeline, Activities, Responsibilities, Outcomes.

The timeline, objectives, and milestone are coordinated with persons responsible and contributors to each activity and objective in Table 3. Objectives 1, 2, and 3 establish the development, psychometric foundation, and technical merits of the CBAS. Objective 4 establishes the actual CBAS technology. To improve clarity and concision, the timeline of Objective 4 is integrated with Objectives 1, 2, and 3 within Table 3 (below).

Table 3. Timeline, Responsibilities, and Contributions to Project Activities

Start-up

Activity

Timeline

Responsible

Contributors

Establish Webpage

9/06-10/06

Christ

UMN Web Design Team

Recruit Advisory Board

9/06-10/06

Christ

Taylor, Ysseldyke & RAs

Recruit Item Writers

9/06-12/06

Christ

RAs

Purchase Equipment

9/06-11/06

Christ

None & UMN staff

Finalize School Sites

9/06-11/06

Christ

Ysseldyke & RAs

Milestone #1: established administration of grant activities in prep. for Objectives 1-4.

 

Objective 1 & 4: Define Measurement Targets, Hierarchy, and Items

Activity

Timeline

Responsible

Contributors

1) Research Review

9/06-11/06

Christ

RAs

Review Responsibilities

11/06

Christ

Taylor & Advisory Board

Milestones #2: advisory board will evaluate and report on the conception and design of the project to establish clarity of understanding and recommendations for improvements

2) Develop Skills Hierarchy

10/06-11/06

Christ

Taylor, Experts, & RAs

Review Progress

11/06

Christ

Taylor & Advisory Board

Milestones #3: the draft of Technical Report #1 to define early reading constructs and a priori skills hierarchy

3) Develop Item Bank

11/06-8/07

Christ

Teachers, Experts, RAs

Review Progress

8/07

Christ

Taylor & Advisory Board

Milestones #4: final approval of Technical Report #1 by the Advisory Board by 8/07; the item bank will be complete and ready for field-testing by 8/07; arrangements for field testing are finalized (schools, parent consent, IRB approvals, schedule, etc.)

 

Objective 2 & 4: Develop Computer Adaptive Test for Reading Skills Analysis

Activity

Timeline

Responsible

Contributors

4) Field Sample Item Bank

5/07-10/07

Christ

Weiss & RAs

5) CAT Analysis/Simulation

10/07-11/07

Christ

Weiss & RAs

Review Progress

11/07

Christ

Taylor & Advisory Board

Milestones #5: complete dataset for 1,000-1,500 items responses across 300-600 first & second grade students 10/07; draft Technical Report #2 will include IRT parameters and CAT simulations outcomes by 11/07; arrangements for CAT live testing are finalized

6) CAT Live Testing/Anal.

11/07-2/08

Christ

Weiss, RAs

Milestones #6: complete dataset for CAT responses from 150-250 students by 2/08; final analysis of CAT for summative assessments by 2/08; final approval of Technical Report #2 and CBAS by the Advisory Board by 3/08, including CAT Live Testing/Simulation

 

Objective 3 & 4: Develop Adaptive Self Referenced Test (ASRT) for Progress Monitoring

Activity

Timeline

Responsible

Contributors

7) Analysis/Simulation ASRT

1/08-2/08

Christ

Weiss & RAs

8) ASRT Live Testing

2/08-6/08

Christ

Weiss & RAs

9) Analysis ASRT

6/08-8/08

Christ

Weiss & RAs

Review Progress

8/08

Christ

Taylor & Advisory Board

Milestones #7: complete dataset for ASRT from 75-125 students by 6/08; ASRT data analyzed and integrated; final approval of Technical Report #3 and CBAS by Advisory Board by 12/07; final CBAS for CAT and ASRT with Technical Manual by 8/08